October 29, 2026
Next Tuesday, November 10, Little Egg Harbor Township holds a Zoom hearing on lagoon dredging in two Mystic Island sections. The dredging money was authorized in 2021, and contractors began moving equipment that fall. Five years later, the township's Certified Finance Officer and Tax Assessor will hold hearings on project costs for the Atlantis Maintenance Dredging Project at 5 p.m. and for the Mystic Island West Phase I project at 6 p.m.
For anyone buying or selling a lagoon-front home in those sections this fall, that timing matters more than the dredging does. The final per-lot figure has not been confirmed.
Little Egg Harbor pays for lagoon dredging with bonds and charges the cost back to the lots that benefit. Ordinance 2021-10 authorized up to $1,525,000 for Atlantis. Ordinance 2021-09, later amended by Ordinance 2021-20 to swap two lots in and two out, authorized up to $8,550,000 for Mystic Island West Phase I. Both ordinances call those totals estimated costs, and both expect the township's own contribution to be zero.
The split works the same way in both. In the language of Ordinance 2021-10:
"said assessment to be computed by the Township on the basis of an equal share per tax lot."
The November 10 hearings cover the project costs that the dollar amount will be built from.
Mystic Island's neighbors have been through this before, and their timeline shows how far apart the work and the bill can land. Jersey Shore Online reported in June 2021 how the Osborn Island project ran:
Atlantis and West Phase I are on a longer version of the same calendar. In October 2021, The SandPaper reported that the township had hired JCP Group of Blackwood, with $8,075,000 of the work for Mystic Island West Phase I and $1,275,000 for Atlantis. A month later, the paper reported the contractor mobilizing equipment in Atlantis. The project-cost hearing for that work comes five years after the equipment arrived. Any house in those sections that changed hands in between carries this lag.
Here are the four sections side by side. The first two figures were confirmed. The last two are Haines' 2021 estimates, not final assessments.
| Section | Lots sharing the cost | Per-lot assessment | Status |
|---|---|---|---|
| Osborn Island | 327 | $5,056 | Confirmed, billed starting 2021 |
| Mystic Island east of Radio Road | 524 | $4,845 | Confirmed |
| Mystic Island West Phase I | Not stated | $8,000 to $9,000 | 2021 estimate |
| Atlantis | 134 waterfront homes | $11,000 to $12,000 | 2021 estimate |
Haines told Jersey Shore Online the two newer sections would cost more because there was more material to remove and more to truck away. Atlantis also had the fewest lots, with only 134 waterfront homes expected to share the cost. The contract amount reported for Atlantis was lower than the cap, and the final cost and the final count of assessed lots are still to be confirmed.
The township's February 19, 2026 agenda proposed reinstating delinquent installment plans for the earlier Radio Road East and Osborn Island assessments through November 10, 2026.
The topic comes up on paper during a sale through the state's Seller's Property Condition Disclosure Statement. Question 95 asks whether the seller knows of any public improvement assessments against the property that remain unpaid. Question 96 asks about mortgages, encumbrances or liens.
There's a near-term paperwork wrinkle too. On October 25, the township said the Detailed Transaction Report had been left out of the hearing notices it mailed, and that the report would go up on its website on October 26. The Clerk's Office asks callers to say whether their question is about the Atlantis Project or Mystic Island Phase 1. The number is 609-296-7241, ext. 230.
The program runs section by section, and each section has to want it. Haines told Jersey Shore Online the township polls each section and goes ahead only with a favorable vote. One Mystic Island owner who voted yes, Dave Silva, put the case this way in that report: "People buy on a lagoon to get water access and I want everyone to enjoy the water."
Mystic Island West Phase 2 didn't get that vote. The township's March 2026 draft reexamination report says most respondents to a poll posted April 25, 2022 opposed moving ahead, and that the township would keep reviewing all available funding sources. In August 2025, The SandPaper reported residents bringing up future dredging at a township meeting, where a representative of a local homeowner group urged the township to consider funding options. So lagoon lots in Mystic Island fall into three groups right now. Osborn Island and Radio Road East owners are paying off confirmed assessments. Atlantis and West Phase I owners are heading into project-cost hearings. Phase 2 lagoons are tied to a project the township describes as still under funding review.
Which hearing applies to a given address? The Atlantis section hearing is at 5 p.m. and the Mystic Island West Phase I hearing is at 6 p.m., both on November 10 over Zoom. Notices with the Zoom details went to affected owners by mail. Owners can also reach the Clerk at [email protected].
Can grant money lower the assessment? Both ordinances say any grant money received for the dredging would go toward reducing the bonds or paying project costs. Neither ordinance says a grant was actually awarded.
How do the ordinances describe the assessment? Both ordinances describe the assessment as an equal share per tax lot.
If you're listing or shopping for a lagoon home in Atlantis or west of Radio Road, The Scott Reighard Real Estate Team can help with your pricing and timeline. Start with a free home valuation.
Stay up to date on the latest real estate trends.
We specialize in bringing you the best homes for sale and real estate listings in the area. Whether you are buying a home, selling a home or need help securing a Home Mortgage, I've got you covered. Contact Us today!